Construction
Progress.

At Hillgrove, construction is well underway and we want to make sure you know what’s happening at every step. Below, keep track of the percentage of works completed. Or see the Bird’s iView.

Active:

Stage 12 - Bottlebrush, Maple, Grevillea & Magnolia Release

Construction Started May 2021

Estimated Titles Due

January/ February 2022

Estimated Settlement Due

January/ February 2022

100
60
Civil
Registration
Civil Phase
100%

Site Establishment

Site Establishment

This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

 

Bulk Earthworks

Bulk Earthworks

The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

 

Drainage Works

Drainage Works

The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

 

Sewer Works

Sewer Works

The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

 

Water & Gas Retriculation

Water & Gas Retriculation

The provision of water and gas pipelines with a connection to each lot.

 

Subgrade Placement Works

Subgrade Placement Works

The engineered material that provides a firm base underneath a constructed road pavement.

 

Electrical & NBN

Electrical & NBN

The supply of electricity and NBN (high speed internet) to each lot.

 

Footpaths/ Asphalt/ Linemarking

Footpaths/ Asphalt/ Linemarking

The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.

 

Practical Completion

Practical Completion

The completion of the construction works.

 

Registration Phase
60%

Statement of Compliance

Statement of Compliance

The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

 

Lodge Plan of Subdivision

Lodge Plan of Subdivision

The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

 

Titles

Titles

The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.

 

Settlement

Settlement

The legal transfer of the residential lot from the developer to the prospective home owner.

View Details

Stage 13 - Lilly Pilly & Blackwood Releases

Construction Started May 2021

Estimated Titles Due

January/ February 2022

Estimated Settlement Due

January/ February 2022

100
60
Civil
Registration
Civil Phase
100%

Site Establishment

Site Establishment

This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

 

Bulk Earthworks

Bulk Earthworks

The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

 

Drainage Works

Drainage Works

The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

 

Sewer Works

Sewer Works

The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

 

Water & Gas Retriculation

Water & Gas Retriculation

The provision of water and gas pipelines with a connection to each lot.

 

Subgrade Placement Works

Subgrade Placement Works

The engineered material that provides a firm base underneath a constructed road pavement.

 

Electrical & NBN

Electrical & NBN

The supply of electricity and NBN (high speed internet) to each lot.

 

Footpaths/ Asphalt/ Linemarking

Footpaths/ Asphalt/ Linemarking

The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.

 

Practical Completion

Practical Completion

The completion of the construction works.

 

Registration Phase
60%

Statement of Compliance

Statement of Compliance

The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

 

Lodge Plan of Subdivision

Lodge Plan of Subdivision

The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

 

Titles

Titles

The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.

 

Settlement

Settlement

The legal transfer of the residential lot from the developer to the prospective home owner.

View Details

Completed:

Stage 1 - Willow Release

Titles

May 2019

Settlement

June 11, 2019

Stage 2 - Sheoak Release

Titles

May 2019

Settlement

June 11, 2019

Stage 3 - Garden & Myrtle Releases

Titles

May 2019

Settlement

June 13, 2019

Stage 4 - Elm & Gum Releases

Titles

June 2019

Settlement

July 1, 2019

Stage 5 - Evergreen, Reed & Heath Releases

Titles

September 2019

Settlement

September 30, 2019

Stage 6 – Blossom, Leafy, Ironbark & Trail Releases

Titles

September 2020

Settlement

September 28, 2020

Stage 7 - Cedar & Olive Releases

Titles

August 2020

Settlement

August 11, 2020

Stage 8 - Parkwalk, Footbridge & Truffle Releases

Titles

January 2021

Settlement

January 2021

Stage 9 - Bluegum, Pink Heath & Banksia Releases

Titles

January 2021

Settlement

January 2021

Stage 10 - Jacaranda & Waratah Releases

Estimated Titles Due

August 2021

Estimated Settlement Due

August 2021

Stage 11 - Pine Release & Eucalypt Releases

Estimated Titles Due

October 2021

Estimated Settlement Due

November 2021