Construction
Progress.
At Hillgrove, construction is well underway and we want to make sure you know what’s happening at every step. Below, keep track of the percentage of works completed. Or see the Bird’s iView.
At Hillgrove, construction is well underway and we want to make sure you know what’s happening at every step. Below, keep track of the percentage of works completed. Or see the Bird’s iView.
Construction Started November 2017
Titles
May 2019
Settlement
June 11, 2019
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
June, 2019
Construction Started November 2017
Titles
May 2019
Settlement
June 11, 2019
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
June, 2019
Construction Started March 2018
Titles
May 2019
Settlement
June 13, 2019
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
June, 2019
Construction Started April 2018
Titles
June 2019
Settlement
July 1, 2019
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
July, 2019
Construction Started May 2018
Titles
September 2019
Settlement
September 30, 2019
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
September, 2019
Construction Started December 2019
Titles
September 2020
Settlement
September 28, 2020
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
September, 2020
Construction Started September 2019
Titles
August 2020
Settlement
August 11, 2020
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
August, 2020
Construction Started July 2020
Titles
January 2021
Settlement
January 2021
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
January, 2021
Construction Started July 2020
Titles
January 2021
Settlement
January 2021
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
January, 2021
Construction Started December 2020
Titles
August 2021
Settlement
August 2021
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
September, 2021
Construction Started March 2021
Titles
October 2021
Settlement
November 2021
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
December, 2021
Construction Started May 2021
Titles
March 2022
Settlement
April 2022
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
April 2022
Construction Started May 2021
Titles
March 2022
Settlement
April 2022
Site Establishment
Site Establishment
This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.
Bulk Earthworks
Bulk Earthworks
The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.
Drainage Works
Drainage Works
The provision of underground drainage and channel/ retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.
Sewer Works
Sewer Works
The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.
Water & Gas Retriculation
Water & Gas Retriculation
The provision of water and gas pipelines with a connection to each lot.
Subgrade Placement Works
Subgrade Placement Works
The engineered material that provides a firm base underneath a constructed road pavement.
Electrical & NBN
Electrical & NBN
The supply of electricity and NBN (high speed internet) to each lot.
Footpaths/ Asphalt/ Linemarking
Footpaths/ Asphalt/ Linemarking
The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement a road.
Practical Completion
Practical Completion
The completion of the construction works.
Statement of Compliance
Statement of Compliance
The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.
Lodge Plan of Subdivision
Lodge Plan of Subdivision
The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.
Titles
Titles
The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.
Settlement
Settlement
The legal transfer of the residential lot from the developer to the prospective home owner.
April 2022
Thanks for your interest in . Fill out your details and a member of our team will be in touch shortly with more information.